49-2018: Harwich Harbour maintenance dredging – Harwich Haven berths and approaches

Mariners are advised that on or about the 12th November 2018 the plough dredger FORTH DRUMMER will commence maintenance dredging of the Harwich Haven berths and approaches for a period of approximately 16 days.

Mariners are also advised that on or about the 14th November 2018 the trailer suction dredger BARENT ZANEN will commence maintenance dredging of the Harwich Haven berths and approaches for a period of approximately 14 days.

Survey work in regard to the dredging operations will be conducted by the vessel SHAMROCK.

Material from these areas will be disposed to the new Harwich Haven disposal site.

Detailed dredger movements can be obtained from Harwich VTS on VHF Channel 71.

Lights and shapes as required by Collision Regulations will be exhibited and a listening watch on VHF Channel 71 will be maintained throughout.

 

Notice to Mariners 48 of 2018 is cancelled.