24-2019: Maintenance dredging – deep water channel

Mariners are advised that on or about the 18th May 2019 the trailer suction dredger HAM 316 will commence maintenance dredging of the Harwich approaches on the eastern side of the channel between the Walker Buoy and South Shipwash Buoy for approximately 3 days.
Material will be disposed of to the Inner Gabbard East disposal site.
Mariners are also advised that the trailer suction dredger HAM 316 will then commence maintenance dredging of the Harwich main approach channel edges in the vicinity of No.1 and No.2 Buoys for approximately 2 days.
Material from these areas will be disposed to the Harwich Haven disposal site.

Detailed dredger movements can be obtained from Harwich VTS on VHF Channel 71.
Lights and shapes as required by Collision Regulations will be exhibited and a listening watch on VHF Channel 71 will be maintained throughout.

Notice to Mariners No. 22 of 2019 is cancelled